Worked feature example

Cost estimation

Estimate the office field with simple unit rates and the installed detailed indicative price list. Inspect item quantities, drilling classes, contingency, VAT and cost indicators.

16Boreholes
-2.41 °CMinimum mean fluid temperature
16.03 °CMaximum mean fluid temperature
3Variants compared
01 / Project

What the example does

What does the office field cost to build? BoreTherm estimates it with simple unit rates and with a detailed price list of the items of a borehole field: site works, drilling by ground class, probes, grouting, connections, fluid, design and permits, with contingency and VAT.

Inputs

InputValue
Field16 boreholes, 4 × 4 rectangle, spacing 6.0 × 6.0 m
Boreholeslength 150.0 m, top 4.0 m below the surface, diameter 140 mm
Constructionsingle U, PE pipe 32 × 2.9 mm, shank spacing 70 mm, grout 1.60 W/(m·K)
Groundthermal conductivity 2.60 W/(m·K), heat capacity 2.20 MJ/(m³·K), surface temperature 9.0 °C, geothermal heat flux 0.060 W/m²
Fluid and flow25 % monopropylene glycol, 0.50 l/s per borehole
Loadsmonthly: heating 200 MWh, hot water 8 MWh and cooling 45 MWh per year; peaks 100 kW heating and 45 kW cooling for 6 h
Heat pumpseasonal performance factors 3.8 heating, 2.8 hot water, 5.0 cooling
Design limitsmean fluid temperature between −3.0 °C and 20.0 °C
Period25 years
Simple modelunit rates per borehole, per metre drilled and per metre of trench
Detailed modelindicative price list Germany 2026, 10 % contingency, 19 % VAT

Run the example in BoreTherm

  1. Open Economics → Borefield costs. Choose the simple or the detailed model.
  2. In the detailed model, check the quantities, the drilling classes and the price list; any rate can be edited.
  3. Press Size borehole length to price the sized field, or Calculate for the input design.
02 / How BoreTherm calculates it

How the estimate is built

1 Quantities2,464 m drilled for 2,400 mactive; trench, fluid2 Unit pricesprice list per item anddrilling class3 Cost groupssite, drilling, probes,connection, fluid, design4 Contingency+ 10 % of the net→ 290,227 EUR5 VAT+ 19 %→ 345,371 EUR gross6 Indicatorsper metre, per kWof extractionDetailed: 345,371 EUR gross; simple: 131,200 EUR
The detailed estimate of the office field.
  1. QuantitiesFrom the design: drilled metres (including the top 4 m), number of probes, trench and connection lengths, fluid volume.
  2. Unit pricesEach item has a price in the list; drilling depends on the ground class.
  3. Cost groupsDrilling is the largest group (155,232 EUR), then probes, grouting and tests (46,532 EUR).
  4. ContingencyA share of the net cost for the unforeseen.
  5. VATAdded as an explicit input.
  6. IndicatorsCost per metre and per kW help to compare with other projects.
03 / In BoreTherm

The example in BoreTherm

Economics → Borefield costs: the simple model.
Economics → Borefield costs: the simple model.
The detailed model: items, quantities and cost groups.
The detailed model: items, quantities and cost groups.
04 / Results

Calculated results

Calculated with BoreTherm for every variant of the example. Displayed values are rounded.

EstimateCurrencyNetContingencyNet totalVATGross
simpleEUR131,200.000.00131,200.000.00131,200.00
detailed price listEUR263,843.1826,384.32290,227.4955,143.22345,370.72
customEUR227,200.0022,720.00249,920.0047,484.80297,404.80

Detailed price list: Germany 2026 (indicative); date 2026-10.

Cost groupNet amount [EUR]
Site and preliminary works7,000.00
Drilling155,232.00
Probes, grouting, tests46,532.28
Horizontal connection23,120.00
Heat-carrier fluid4,973.15
Design, permits, ancillary26,985.74
Cost estimation results plotted from BoreTherm output
Chart of the BoreTherm results in the tables of this section.

Temperatures by variant

VariantBoreholesLength H [m]Tf min [°C]Tf max [°C]Rb* [m K/W]Pump [W]Design limits
edited unit rate16150.000-2.41316.0260.11943,033.2within limits
detailed price list16150.000-2.41316.0260.11943,033.2within limits
simple unit rates16150.000-2.41316.0260.11943,033.2within limits
05 / Discussion

What the example shows

The simple and the detailed estimate cover different scopes, so their difference is not a quote comparison: the simple rates cover a fixed cost, the boreholes, drilling and trench only. The detailed result prices 2,464 drilled metres for 2,400 active metres and adds contingency and VAT.

These are indicative estimates from the program's price list, with its name and date. They are not supplier quotations.