BTES operation
Generates one year of seasonal operation of a borehole thermal energy store, repeated every year. Choose Charge, Rest or Discharge for each calendar month and whether the series prescribes the inlet temperature or the ground load; enter for charging and for discharging the inlet temperature or load, the flow (whole field or per borehole; volume or mass flow) and the daily operating hours, and the row step. Charging runs the connections as drawn (direction +1), discharging reverses them (direction −1); the pump is off at rest and outside the daily hours. Review the preview (months, operating hours and, with a prescribed load, the energy per year) before Generate: the series replaces the project's time-series loads. Use in the dynamic model also switches the borehole model to Dynamic with inlet, flow and flow direction from the series. The flow-direction rule itself (fixed, from the time series, automatic with a reversal hysteresis and a minimum time between reversals) is set on Design limits & simulation. The storage results count all charged and discharged heat; there is no return-temperature cut-off.
Step-by-step workflows · Menus and keyboard

| Control | Meaning / action | Unit | Range / choices | Example value |
|---|---|---|---|---|
| January | Charge, rest or discharge in this calendar month of the generated annual schedule. | Charge / Rest / Discharge | ||
| February | Charge, rest or discharge in this calendar month of the generated annual schedule. | Charge / Rest / Discharge | ||
| March | Charge, rest or discharge in this calendar month of the generated annual schedule. | Charge / Rest / Discharge | ||
| April | Charge, rest or discharge in this calendar month of the generated annual schedule. | Charge / Rest / Discharge | ||
| May | Charge, rest or discharge in this calendar month of the generated annual schedule. | Charge / Rest / Discharge | ||
| June | Charge, rest or discharge in this calendar month of the generated annual schedule. | Charge / Rest / Discharge | ||
| July | Charge, rest or discharge in this calendar month of the generated annual schedule. | Charge / Rest / Discharge | ||
| August | Charge, rest or discharge in this calendar month of the generated annual schedule. | Charge / Rest / Discharge | ||
| September | Charge, rest or discharge in this calendar month of the generated annual schedule. | Charge / Rest / Discharge | ||
| October | Charge, rest or discharge in this calendar month of the generated annual schedule. | Charge / Rest / Discharge | ||
| November | Charge, rest or discharge in this calendar month of the generated annual schedule. | Charge / Rest / Discharge | ||
| December | Charge, rest or discharge in this calendar month of the generated annual schedule. | Charge / Rest / Discharge | ||
| Prescribe: | What the series prescribes: the inlet temperature of the fluid (the dynamic model computes the heat rate), or the heat rate into the ground. | Inlet temperature / Ground load | ||
| Flow unit: | Unit of the flows below. A mass flow is stored as it is and converted with the density at the inlet temperature of each step. | l/s / m³/h / l/min / m³/s / kg/s (mass flow) / kg/h (mass flow) / t/h (mass flow) | ||
| Flow refers to: | The flows are the pump's flow (whole field) or the mean flow through one borehole. | Whole field / Per borehole | ||
| Step: | Step between two rows of the series (the dynamic model's control step must fit it). | 5 min / 10 min / 15 min / 20 min / 30 min / 60 min | ||
| Use in the dynamic model | Switches the borehole model to Dynamic and sets its inlet, flow and flow direction to follow the time series. Off: only the loads are replaced. | |||
| Btes charge tin | Inlet temperature while charging. | °C | -30 to 150 | 70 |
| Btes charge load | Heat rate injected into the ground while charging. | kW | 0 to 1e+06 | 100 |
| Btes charge flow | Flow in the unit chosen above. | l/s | 0 to 1e+06 | 0.5 |
| Btes charge from | Start of the daily operation (0 - 24 = all day). | h | 0 to 24 | 0 |
| Btes charge to | End of the daily operation (an end before the start runs over midnight). | h | 0 to 24 | 24 |
| Btes discharge tin | Inlet temperature while discharging. | °C | -30 to 150 | 30 |
| Btes discharge load | Heat rate extracted from the ground while discharging. | kW | 0 to 1e+06 | 100 |
| Btes discharge flow | Flow in the unit chosen above. | l/s | 0 to 1e+06 | 0.5 |
| Btes discharge from | Start of the daily operation (0 - 24 = all day). | h | 0 to 24 | 0 |
| Btes discharge to | End of the daily operation (an end before the start runs over midnight). | h | 0 to 24 | 24 |
| Reset view | Show all data (also: double-click the plot). | |||
| Chart style button | Chart style: title, axis titles, legend, colours, line widths and markers, fonts, grid and background (also in the chart's context menu). | |||
| PNG… | Export the plot as a PNG image. | |||
| SVG… | Export the plot as a vector SVG image (for Word, Inkscape, …). | |||
| PDF… | Export the plot as a vector PDF. | |||
| CSV… | Export the plotted data as CSV. | |||
| Generate | Generate the configured output. In BTES this creates the operation series; in Report it writes the selected report files. | |||
| Cancel | Close without accepting unapplied edits. | |||
| Btes charge tin | Inlet temperature while charging. | °F | -22 to 302 | 158 |
| Btes charge load | Heat rate injected into the ground while charging. | MW | 0 to 1000 | 0.1 |
| Btes discharge tin | Inlet temperature while discharging. | °F | -22 to 302 | 86 |
| Btes discharge load | Heat rate extracted from the ground while discharging. | MW | 0 to 1000 | 0.1 |