Borefield costs
Choose a simple or detailed cost estimate. Enter prices, currency, contingencies and tax consistently. Prices are illustrative and need local replacement. Optimization can minimize total cost, drilling or other supported objectives. The page shows the estimate of the current field; the report has a cost section, and Optimize and the heating-system comparison use the same estimate.
Step-by-step workflows · Menus and keyboard

| Control | Meaning / action | Unit | Range / choices | Example value |
|---|---|---|---|---|
| Simple | A few prices: fixed, per borehole, per metre, per circuit, per metre of trench, with contingency and VAT. | |||
| Detailed | An itemised price list: site, drilling by geology, probes and grout, horizontal connection, fluid, design and permits. | |||
| Library | The built-in list and the price lists saved in your library folder (Documents\BoreTherm\Price lists). | |||
| Load… | Load a price list (.btcost) or the price list of another project into this project (switches to the detailed model). | |||
| Save as… | Save this project's price list as a file (.btcost) to use it in other projects. | |||
| Reset to built-in | Use the built-in list "Germany 2026 (indicative)" again (your changes to the list are discarded). | |||
| Undo | Restore the cost settings from before. | |||
| × | Hide this note. | |||
| Name: | Name of the price list (shown in the report). | |||
| Currency: | Currency code of the price list, e.g. EUR or CHF. | |||
| Price date: | Date of the prices (year-month). The report shows it; prices older than two years give a hint (set an index factor). | |||
| Country: | Country of the project: items bound to a country (the German mining-law notification for boreholes deeper than 100 m) apply only there. | Germany / Austria / Switzerland / Other | ||
| Regional factor: | Regional factor: multiplies every price except percentages (BKI regional factors are about 0.8–1.4). | 0.1 to 5 | 1 | |
| Index factor: | Index factor: escalation from the price date to the date of the estimate (e.g. from a construction price index). | 0.1 to 5 | 1 | |
| Contingency: | Contingency on the net sum. | % | 0 to 100 | 10 |
| VAT: | Value added tax on the net total (shown as gross; not used for the ranking). | % | 0 to 100 | 19 |
| Fixed: | Fixed cost of the field: mobilisation, permits, design, manifold… as one sum. | € | 0 to 1e+09 | 5000 |
| Per borehole: | Cost per borehole to drill: rig set-up, tests, probe head, welds… (existing boreholes are not counted). | € | 0 to 1e+09 | 800 |
| Per metre: | Drilling incl. probe and grout per metre (all-in; typical 50–120 €/m). | €/m | 0 to 1e+06 | 45 |
| Length basis: | The length the price per metre applies to: the drilled length of the new boreholes (buried depth D, active length H and the foot length), or their active length H as before (projects of earlier versions). | Drilled length (D + H + foot) / Active length H | ||
| Per circuit: | Cost per circuit (parallel string): manifold port, connection pipes, welds. | € | 0 to 1e+09 | 0 |
| Per metre of trench: | Trench incl. sand bed and backfill per metre (the trench is the shortest network connecting the borehole heads and the manifold). | €/m | 0 to 1e+06 | 60 |
| Currency: | Currency code of the project's costs, e.g. EUR or CHF. | |||
| + Item | Add an item of your own to the group of the selected line (lump sum, price 0). | |||
| – Item | Remove the selected item of your own; an item of the list is switched off. | |||
| Reset to list | Reset the selected item to the built-in list: price, quantity and on/off. | |||
| Export CSV… | Write the displayed numerical table to a CSV file using the selected CSV format. | |||
| Foot length: | Inactive length drilled below the active part (probe foot, sump); part of the drilled length D + H + foot. | m | 0 to 100 | 0 |
| Grout excess: | Grout volume factor over the annulus (losses into the formation; 1.2 = +20 %). | 1 to 3 | 1.2 | |
| Pipe routing: | Connection pipes: along the trench (supply to the first and return from the last borehole of each circuit), a fixed length per circuit, or straight lines from the manifold. | Along the trench / Fixed per circuit / Straight from the manifold | ||
| Pipe per circuit: | Connection pipe per circuit (pipe routing "Fixed per circuit"). | m | 0 to 10000 | 0 |
| Detour: | Detour of the trench and the pipes over the straight connections. | % | 0 to 200 | 0 |
| Header length: | Header pipes (one pair) from the manifold to the plant room. | m | 0 to 10000 | 0 |
| Paved share: | Share of the trench under a paved surface (priced with surface restoration). | % | 0 to 100 | 0 |
| TRT count: | Thermal response tests to price (VDI 4640 recommends one above about 30 kW). | 0 to 20 | 0 | |
| Building entries: | Building entries / wall penetrations of the header pipes. | 0 to 50 | 0 | |
| PE-Xa probes | Probes of PE-Xa instead of PE 100-RC (probe price × the factor of the price list). | |||
| Drilling class: | Drilling class of a homogeneous ground, and of layers without a class. | Loose sediments / Mixed / soft rock / Hard rock | ||
| Foot length: | Inactive length drilled below the active part (probe foot, sump); part of the drilled length D + H + foot. | ft | 0 to 328.1 | 0 |
| Pipe per circuit: | Connection pipe per circuit (pipe routing "Fixed per circuit"). | ft | 0 to 32808.4 | 0 |
| Header length: | Header pipes (one pair) from the manifold to the plant room. | ft | 0 to 32808.4 | 0 |