Set permitted patterns, borehole counts, spacing/depth bounds, site/plot dimensions, the objective (Minimise total borehole length, Minimise total cost or Minimise ground-source heat pump life-cycle heat cost) and retained candidates. Start launches a bounded search with progress and cancellation. Begin with the small tutorial before expanding the candidate space.

Step-by-step workflows · Menus and keyboard

Optimization setup in BoreTherm
English GUI; click to enlarge.
Controls captured from the BoreTherm GUI. Ranges are interface bounds; example values depend on the open project.
ControlMeaning / actionUnitRange / choicesExample value
Region:Rectangular plot: layouts within length × width. Site plan: layouts and fills inside the drilling areas of the site plan, outside no-go zones and corridors, with every setback; the trench runs to the connection point.Rectangular plot / Site plan (drilling areas)
Plot length (x):Available land, extent along x.m1 to 500040
Plot width (y):Available land, extent along y.m1 to 500030
Borehole distance min:Minimum allowed distance between the closest boreholes in a result.m1 to 1005
Borehole distance max:Maximum allowed distance between the closest boreholes in a result.m1 to 20012
Layout spacing step:Layout spacing step used to generate candidates; 0 = automatic (coarse 5 m steps, then refined around the best).m0 to 500
Borehole length min:Shortest allowed borehole length.m5 to 200060
Borehole length max:Longest allowed borehole length.m5 to 3000250
Boreholes min:Fewest boreholes considered.1 to 100004
Boreholes max:Most boreholes considered.1 to 1000040
Single boreholeEnables or disables this option.
LineEnables or disables this option.
L-shapeEnables or disables this option.
L2-shape (double L)Enables or disables this option.
U-shapeEnables or disables this option.
Open rectangleEnables or disables this option.
RectangleEnables or disables this option.
CircleEnables or disables this option.
HexagonalSearch hexagonal fields with a centre borehole and rings of 6, 12, 18, ... boreholes.
Concentric ringsSearch equally spaced concentric rings with a centre borehole and 6, 12, 18, ... boreholes per ring. Custom ring counts and radii are not varied.
GridFill the drilling areas with this pattern and try every borehole count, taking the positions spread out as far as possible and, as an alternative, compact (nearest the connection point).
StaggeredFill the drilling areas with this pattern and try every borehole count, taking the positions spread out as far as possible and, as an alternative, compact (nearest the connection point).
Row-wiseFill the drilling areas with this pattern and try every borehole count, taking the positions spread out as far as possible and, as an alternative, compact (nearest the connection point).
PerimeterFill the drilling areas with this pattern and try every borehole count, taking the positions spread out as far as possible and, as an alternative, compact (nearest the connection point).
Angle step:Orientations tried besides those along the edges of the drilling areas, every this many degrees; 0 = along the edges only.°0 to 9015
Edit costs…Close this dialog and open the Borefield costs page (model, prices, price list).
Objective:Life-cycle heat cost uses the Heating-system comparison settings and the coupled heat pump seasonal performance factor (SPF). It ranks monthly-load layouts at their thermally required depth.Minimise total borehole length / Minimise total cost / Minimise ground-source heat pump life-cycle heat cost
Keep best:Number of best candidates returned.1 to 100020
OptimizeValidate the search bounds and start the permitted candidate search.
CancelClose without accepting unapplied edits.
Plot length (x):Available land, extent along x.ft3.3 to 16404.2131.2
Plot width (y):Available land, extent along y.ft3.3 to 16404.298.4
Borehole distance min:Minimum allowed distance between the closest boreholes in a result.ft3.3 to 328.116.4
Borehole distance max:Maximum allowed distance between the closest boreholes in a result.ft3.3 to 656.239.4
Layout spacing step:Layout spacing step used to generate candidates; 0 = automatic (coarse 5 m steps, then refined around the best).ft0 to 1640
Borehole length min:Shortest allowed borehole length.ft16 to 6562197
Borehole length max:Longest allowed borehole length.ft16 to 9843820