The one idea: quantities from the design, prices from a list
BoreTherm does not ask for a lump-sum price of the borefield. It measures the design – metres drilled, boreholes, circuits, trench, grout, fluid – and multiplies each quantity by a unit price. The estimate is a list of lines quantity × unit price; every total follows from the lines. Change the length or the layout and the estimate follows at once, because nothing of the thermal model is recalculated.
Ld = D / cos θ + H + foottotal = q · p · fnet total = net · (1 + contingency)gross = net total · (1 + VAT)D is the buried top part of the borehole above the active length H, θ the tilt from the vertical and foot the length drilled below H; q is a quantity, p its unit price. The probe is the pipe loop in the borehole, the grout the filling around it. The contingency is a reserve for the unforeseen, a percentage of the net.
The net total is the number that drives decisions: the optimizer ranks layouts by it, and the system comparison takes it as the investment of the borefield. VAT only gives the gross shown on the page and in the report (the comparison adds VAT itself when it works with gross prices).
The workflow
There are two cost models. Choose by what you know about the prices, not by the size of the project.
The estimate is computed on Economics › Borefield costs and used in four places:
- Borefield costs: model switch, the five prices or the price list (Load…, Save as…, Library, Reset to built-in), the quantity options (foot length, grout excess, pipe routing, detour, header length, paved share, TRT (thermal response test) count, building entries, PE-Xa, drilling class per ground layer) and the summary with net, contingency, net total, VAT, gross and the indicators.
- After Size borehole length (menu Calculation › Size borehole length) the page also shows the net total with the mean length scaled to the sized H, and the difference to the current design.
- Optimize… (menu Calculation › Optimize) sizes every candidate layout and prices it at its own sized length; the objective Total cost ranks by net total.
- Heating-system comparison prices the borefield again from the current design at every calculation (service life 50 years) and the report has a section Cost estimate.
How the estimate is calculated
Existing boreholes (marked on the Field layout page) are connected but not drilled: they take no drilling, probe, grout or per-borehole cost, but they count for circuits, welds, connection pipes, trench and fluid. Tilted boreholes drill D / cos θ above the active part; their metres per drilling class follow the vertical overlap with each ground layer.
How the cost follows the length and the number of boreholes
Each line scales with one driver. Most of the money follows the drilled metres, but a good part follows the number of boreholes, the circuits and the layout:
| Item kind | Examples (detailed list) | Scales with |
|---|---|---|
| Per field (lump sums) | mobilisation, commissioning, geology and permit, documentation; mining-law notice once a borehole is deep | fixed |
| Per new borehole | rig set-up, probe installation, pressure test (simple: per borehole) | number N |
| Per drilled metre | drilling by class, depth surcharge, grout, probe (simple: per metre) | N × Ld |
| Per circuit | manifold port, welds, connection pipe risers (simple: per circuit) | strings C |
| Per metre of trench / pipe | trench (unpaved, paved), connection pipes, header pair | layout, spacing |
| Per kg of fluid | glycol concentrate (or premix) | pipe volume |
| Percentage | design and supervision: 10 % of A–E; contingency on the net | all of the above |
The link to sizing. The thermal design decides the metres; the cost model only prices them. Size borehole length gives the required H of the current layout, and the Costs page shows what that length costs. The estimate never feeds back into the simulation.
The link to the optimizer. Optimize enumerates layouts on the plot (type, rows, spacing), sizes each one and prices it at its sized length with the project’s cost settings. Every candidate gets the default network (all boreholes parallel, or strings of the boreholes in series of Fluid & flow), and the manifold at the site’s connection point or the head nearest the centroid. Because the cost has steps (the 100 m class, manifold sizes, lump sums), the optimizer does not search with gradients: it compares candidates. Its candidates are vertical and unrotated.
How each result is derived
Detailed model with the built-in list “Germany 2026 (indicative)” (price date 2026-10), example field 16 × 150 m, single U, 25 % monopropylene glycol (MPG), homogeneous ground (class “mixed”).
| Result | How BoreTherm derives it | Example |
|---|---|---|
| Drilled length Ld | Σnew (D / cos θ + H + foot) | 16 × (4 + 150 + 0) = 2,464 m |
| Drilling, by class | drilled metres in each ground layer × class price (homogeneous: one class) | 2,464 m × 55 €/m = 135,520 € |
| Deep boreholes | Ld > 100 m: surcharge on the whole length; one of them triggers the mining-law notice (DE) | 16 deep: 2,464 m × 8 €/m = 19,712 €; notice 1,000 € |
| Probe length Lp | Σ (Ld + 1 m head allowance), priced by probe type | 2,480 m × 5 €/m (single U) = 12,400 € |
| Grout volume | 1.2 × Σ (π/4 db² − nlegs π/4 do²) Ld | 40.76 m³ × 700 €/m³ = 28,532 € |
| Circuits, manifolds, welds | parallel strings C; ⌈C / 16⌉ manifolds; 2 C + wb N + 2 links | C = 16, 1 manifold, 64 welds = 3,200 €; manifold + ports 5,800 € |
| Trench | minimum spanning tree of the heads (+ manifold) × (1 + detour), unpaved / paved | 90 m × 70 €/m = 6,300 € |
| Connection pipes | per circuit: supply to the first + return from the last borehole along the tree, + 2 risers of 1 m | 632 m × 10 €/m = 6,320 € |
| Fluid and glycol | V = probes + pipes + headers + 2 l per port; m = ρ V; glycol = w m | 3.23 m³, 3,315 kg, 829 kg MPG × 6 €/kg = 4,973 € |
| Design and supervision | 10 % of the non-percentage lines of groups A–E | 10 % × 236,857 € = 23,686 € |
| Net → net total → gross | Σ lines; × (1 + contingency); × (1 + VAT) | 263,843 € → 290,227 € → 345,371 € |
| Indicators | net total / drilled m; / active m; / kW peak ground extraction | 117.8 €/m, 120.9 €/m, 3,939 €/kW (73.7 kW) |
The example in numbers
| Estimate | Field | Drilled [m] | Net total | € / drilled m |
|---|---|---|---|---|
| Simple model, the project’s own prices | 16 × 150 m | 2,464 | 131,200 € | 53.2 |
| Detailed model, built-in list | 16 × 150 m | 2,464 | 290,227 € | 117.8 |
| Detailed, at the sized length (Size borehole length) | 16 × 143.7 m | 2,363 | 280,347 € | 118.6 |
| Best layout of the optimizer, simple prices | L-shape, 8 × 213.1 m, 10 m apart | 1,737 | 92,320 € | 53.2 |
| Best layout of the optimizer, detailed prices | L-shape, 8 × 213.1 m, 10 m apart | 1,737 | 202,276 € | 116.5 |
The simple and the detailed model differ here because their prices differ, not their method. The example keeps the four prices of its optimization setup (fixed 5,000 €, 800 € per borehole, 45 € per metre of active length, 60 € per metre of trench, no contingency): an all-in price per metre that is far below the built-in detailed list (117.8 €/m drilled). Check which one stands for your market before you compare layouts or heating systems with it.
The sized length saves 9,881 € against the 150 m of the example. The optimizer finds a layout with fewer, deeper boreholes further apart: 8 × 213.1 m needs 1,737 drilled metres instead of 2,363. Both models rank the same layout first here; with other prices they need not.
Limits to keep in mind
- The built-in list “Germany 2026 (indicative)” holds indicative net prices from public sources, each with a range and a source; prices outside the range are marked amber. It is not a quote. Keep your own lists (.btcost) from your tender results; a price date older than two years gives a hint (set an index factor).
- The estimate covers the borefield up to the header pipes and the building entry. The heat pump, the plant room and the building side are not in it; the system comparison adds them as separate components.
- The quantity options (foot length, grout excess, detour) change the cost only; the thermal model does not see them.
- The trench is the shortest tree connecting the heads; real routes are longer (use the detour) and may be paved (use the paved share).
- Optimizer candidates get the default circuits; the explicit strings of the project and existing boreholes do not carry over to a new layout.
- The simple model has no depth step, no geology and, by default, no price per circuit. Old projects keep their four prices with the active length, 0 % contingency and 0 % VAT, so their optimizer results stay as they were.
Numbers calculated with BoreTherm. Costs calculated with boretherm-cli cost, size and optimize.