What the example does
A thermal response test of 72 hours on one borehole of the office field, with a deliberate interruption of the heater. BoreTherm screens the data, fits the ground conductivity and the borehole resistance with several methods and applies the recommended fit to the design.
Inputs
| Input | Value |
|---|---|
| Field | 16 boreholes, 4 × 4 rectangle, spacing 6.0 × 6.0 m |
| Boreholes | length 150.0 m, top 4.0 m below the surface, diameter 140 mm |
| Construction | single U, PE pipe 32 × 2.9 mm, shank spacing 70 mm, grout 1.60 W/(m·K) |
| Ground | thermal conductivity 2.20 W/(m·K), heat capacity 2.20 MJ/(m³·K), surface temperature 9.0 °C, geothermal heat flux 0.060 W/m² |
| Fluid and flow | 25 % monopropylene glycol, 0.50 l/s per borehole |
| Loads | monthly: heating 200 MWh, hot water 8 MWh and cooling 45 MWh per year; peaks 100 kW heating and 45 kW cooling for 6 h |
| Heat pump | seasonal performance factors 3.8 heating, 2.8 hot water, 5.0 cooling |
| Design limits | mean fluid temperature between −3.0 °C and 20.0 °C |
| Period | 25 years |
| Test | 72 h heating, about 5.9 kW, 0.5 l/s, samples every 2 min; one interruption |
Run the example in BoreTherm
- Open Advanced analysis → TRT evaluation and start the wizard.
- Import the measured series and check the test setup (borehole, fluid, flow).
- Read the quality checks, then evaluate: line source, cylinder source and superposition methods.
- Compare the fits and apply the recommended one to the ground and Rb* of the project.
How a response test is evaluated
- ImportThe measured series is read from a file.
- Quality checksFifteen checks against recommended limits. Two fail here: the heating power varies too much because of the interruption.
- Heat historyThe injected heat per metre is calculated from flow and temperature difference.
- FitThe classical line-source slope is only valid without interruptions; the superposition methods use the whole heat history, including the interruption.
- RecommendThe cylinder source with superposition fits best.
- ApplyThe design is recalculated with the fitted ground.
The example in BoreTherm
Calculated results
Calculated with BoreTherm for every variant of the example. Displayed values are rounded.
| Test | Recommended fit | λ [W/(m K)] | Rb* [m K/W] | T0 [°C] | Quality passed |
|---|---|---|---|---|---|
| synthetic office test | superposition-chs | 2.599 | 0.08496 | 11.300 | No |
| measured sandbox test | superposition-ils | 2.831 | 0.15476 | 22.090 | Yes |
Synthetic test quality checks
| Check | Design limits | Value | Limit | Unit | Finding |
|---|---|---|---|---|---|
| Sampling interval (longest) | pass | 2.000 | 10.000 | min | longest sampling interval 2.0 min |
| Temperature spike screening coverage | pass | 2,907.000 | 1.000 | samples | 2907 samples screened; at least five finite readings in a symmetric window are needed; endpoints are untested |
| Flow and power disturbances | warning | 2.000 | 0.000 | events | 2 operating event(s); raw readings and heat history preserved; review exclusions |
| Test duration (heating) | pass | 72.000 | 48.000 | h | 72.0 h of heating |
| Heating power: standard deviation / mean | fail | 14.606 | 1.500 | % | 14.61 % of the mean power 5878 W (600 s averages) |
| Heating power: largest deviation / mean | fail | 100.803 | 10.000 | % | 100.8 % of the mean power |
| Specific heat rate | pass | 39.179 | 80.000 | W/m | 39.2 W/m (recommended 30 to 80 W/m) |
| Flow: standard deviation / mean | pass | 0.000 | 5.000 | % | 0.00 % of the mean flow 0.500 l/s |
| Reynolds number (turbulent flow recommended) | pass | 19,121.345 | 2,300.000 | Re = 19121 | |
| Time between grouting and test | pass | 7.000 | 5.000 | d | 7.0 days |
| Undisturbed temperature against Ts + q_geo (D + H/2) / lambda | pass | -0.126 | 2.000 | K | T0 = 11.30 degC, expected 11.43 degC |
| Energy balance: measured power against rho cp V dT | pass | -0.013 | 10.000 | % | measured 5877 W, from flow and dT 5878 W |
| Data gaps (longest) | pass | 0.000 | 60.000 | min | no gaps |
| Heating interruptions | warning | 1.000 | 0.000 | 1 interruption(s): the line-source slope (M1) is not valid across them; the superposition methods account for them | |
| Spikes removed (Hampel filter) | pass | 2.000 | 29.110 | 2 sample(s) removed (0.07 %) |
Temperatures by variant
| Variant | Boreholes | Length H [m] | Tf min [°C] | Tf max [°C] | Rb* [m K/W] | Pump [W] | Design limits |
|---|---|---|---|---|---|---|---|
| office, with the fitted ground | 16 | 150.000 | -0.790 | 15.821 | 0.0850 | 3,033.2 | within limits |
| office, before the test (λ 2.2) | 16 | 150.000 | -3.434 | 16.799 | 0.1196 | 3,033.2 | limits exceeded |
| sandbox borehole | 1 | 18.300 | 15.789 | 26.652 | 0.2025 | 18.7 | limits exceeded |
What the example shows
The fit gives λ = 2.60 W/(m·K) and Rb* = 0.085 m·K/W, against the 2.2 W/(m·K) assumed before the test. With the measured values the office field meets its limits (−0.79 °C instead of −3.43 °C).
Two quality checks fail because of the deliberate interruption. A fitted value is available, but the failed checks are part of the record: such a test should be reviewed before its result is used.